Kosy Group held the 2021 Review and 2022 Target Plan Conference
At Emeralda Ninh Binh Resort, on January 15, 2022, Kosy Group held the 2021 Review and 2022 Target Plan Conference. In attendance were the Executive Board: Chairman/General Director Nguyen Viet Cuong, Vice Chairman Nguyen Thi Hang and 9 Deputy General Directors in charge of the Group’s activities. In particular, the conference gathered hundreds of employees […]
Kosy Group officially connected Nam Pac 2 Hydropower Plant to the national power grid
On December 1, 2021, Kosy Group officially put Nam Pac 2 Hydropower Plant into operation to generate electricity and connected it to the national power grid. This is a milestone affirming Kosy Group’s capacity in the field of hydropower in addition to the successful implementation of wind power projects and real estate. Built in the […]
Completion and official commercial power generation of Kosy Bac Lieu wind power plant
On October 30, 2021, all turbines of Kosy Bac Lieu Wind Power Plant phase 1 – with a capacity of 40.5 MW, owned by Kosy Bac Lieu Wind Power Joint Stock Company – a member of Kosy Group investment, officially recognized commercial operation (COD). The event marks a strategic step forward for Kosy Group in […]
Kosy Group CEO Nguyen Viet Cuong: “Have the courage to succeed”
“It seems that the book has awakened me and completely changed my thinking, aroused my passions and desire to do something great, assert myself. I realized that a new business was really the way for me and I knew what I wanted, what I needed, and what I had to do to be successful.” Those […]
Kosy Bac Lieu Wind Power Plant: Completed turbine installation, ready for date of power generation
On September 28, 2021, the Kosy Bac Lieu Wind Power Plant project phase 1 (installed capacity 40.5 MW) officially completed the installation of all turbines, other stages of the project are being rushed. implemented, ready to put the plant into operation and power generation before October 31, 2021. From the spirit of overcoming difficulties, the […]
Kosy Group accelerates the construction progress of Kosy Bac Lieu Wind Power Plant before ‘G hour’
Kosy Bac Lieu Wind Power Plant phase 1 (capacity of 40 MW) is located in Hoa Binh district, Bac Lieu province, invested by Kosy Bac Lieu Wind Power Joint Stock Company – a member of Kosy Group. The project has a total investment of 1,600 billion VND, started construction from October 2020. All turbines of […]
Kosy Joint Stock Company reached the Top 10 fastest growing enterprises in Vietnam in 2021
The FAST500 Ranking announcement ceremony was organized by Vietnam Assessment Report Joint Stock Company (Vietnam Report) and Vietnamnet online newspaper on April 24, 2021. This is a ranking built based on independent research and evaluation results of Vietnam Report, officially announced for the first time in 2011. List of Top 10 fastest growing enterprises in […]
Kosy Group’s 13-year journey: Effort and sublimation
With ambition, determination and pursuit of goals, Mr. Nguyen Viet Cuong – Chairman of Kosy Group has made Kosy a leading corporation in the field of real estate and renewable energy in Vietnam after 13 years of establishment (March 10, 2008 – March 10, 2021). Let’s listen to the sharing of the head of Kosy […]